If there is a change to REPORT_INFO, the first report deployment after installing the IC must include all reports. (If it is not possible to deploy all the reports at once, deploy the critical online reports first, and then the batch reports.)
After an IC is installed, the first report deployment checks for a change to REPORT_INFO and then checks whether the report deployment is using the Rebuild option. If there is a change to REPORT_INFO and the report deployment is not a Rebuild, a message is logged in the Build Log. The message inform you that REPORT_INFO has changed.
The following message appears in the Build Log.
“New REPORT DUMPINFO is available, all reports require a REBUILD”
Action required:
Wait for the deployment to complete.
Deploy all reports with the Rebuild option.
Recommendation:
The first report deployment after an IC update must be a build with the Rebuild option. This applies to the source application used in Runtime Transfers as well.
If you are performing the first deployment of the source application for the Runtime Transfer after an IC update and you see the message in the Build log, you must perform another deployment with the Rebuild option before you perform the transfer to deploy the target system.
If you see the message in the Build log and have included all the reports within a system build, perform another report build with the Rebuild option only if the last report build was done with the Build option.